Key Transport & Strategy members were involved in the development and delivery of the Caulfield to Dandenong (CTD) Project, the largest and most complex of the Level Crossing Removal Project (LXRP) portfolio.
The project included 9 level crossing removals, as well as the first brownfields whole-of-corridor rail upgrade (75kms) for signalling, power and overhead electrification to enable running of High Capacity Metro Trains (HCMT) and High Capacity Signalling (HCS).
This transformational project involved many firsts for Melbourne, including developing the first rail-over level crossing solution (Sky Rail) with fully integrated slab track, the first project to be delivered under the new major projects guideline of the Office of the National Rail Safety Regulator (ONRSR) and the Systems Engineering and Systems Assurance Framework of DOT, as well as the first project to introduce modular 4MW substations and modular signalling Relocatable Equipment Buildings (REBs) from an innovation’s perspective.
The project’s innovative approach won it many awards, including an Engineering Excellence award for Engineers Australia in 2020, awards from Infrastructure Partnerships Australia, the Government Partnership Excellence Award, the inaugural Industry Choice Award.
Our Role in the Project
Our T&S representatives held a variety of senior positions on the project and were responsible for leading roles in the bid and delivery phases, holding roles such as the MTM lead responsible for scope management, commercial lead, Interface & Integration AMT representative, Alliance commercial manager, sub-alliance ALT, and Signalling Manager.
The role involved managing a complex program to deliver multi-disciplinary works concurrently across 5 separate work fronts, many activities sharing resources and plant etc, as the scale of works in each area were significant and resources constrained. The role also included construction staging, site planning and workgroup management, disruptions and occupations planning, testing & commissioning programs, handover requirements to ensure impacts on train operations and the public is minimized but also to ensure program delivery for the 5 areas (often with several critical path activities within each area). Over the busiest 14- month period of the project, over 400 separate occupation days were delivered across the 5 project areas.
All this work culminated in design approvals, safety case, residual risk register and engineering change notifications, which our T&S member as MTM lead was responsible for consolidating and presenting to MTM Change Control Board for approval.
Project Challenges & Achievements
The scope had significant complexities, level crossing removal on the busiest and narrowest corridor required an innovative approach to construction methodology.
At the same time ONRSR introduced the requirements of the Major Projects Guideline and the first project required to deliver in line with a Systems Engineering and Systems Assurance approach. These processes were still being developed and matured in parallel to CTD delivery.
Another complexity was CTD had to deliver infrastructure to cater for introduction of the HCMT, which was being delivered via a PPP independent of CTD. The TOC for CTD was undertaken a year prior to HCMT contract award, which came with uncertainty the technical interface and specific requirements. Key T&S members were driving force in developing Interface Control Documents, Interface Specifications and other interface tools facilitating the integration of State portfolio objectives.
The scale of this project meant that we had to interface with a multitude of stakeholders with both State and private entities. across five councils, as well as major utility companies and local community groups. This all required a systematic and robust stakeholder management plan, interface and integration framework and consistent requirements management. This fell under our T&S member in the role of Interface & Integration Manager.
Our approach to Teamwork, Cooperation, and Innovation
As members embedded in the alliance, our approach was (as is our normal approach) to work inclusively, open and transparent. Our ideas and innovations to make the project delivery more efficient, cheaper or easier, were all introduced into the wider team, with a view to maximise value and performance of the alliance. Our representatives were regularly acknowledged for their approach to cooperation and ways to overcome challenges, which at times was challenging, especially for the roles above where our representatives had to manage both alliance and rail operator expectations.
Transport & Strategy are an advisory practice offering services in the management of complex infrastructure projects. We work in transport, rail infrastructure, construction, and telecommunications sectors across Victoria.
We pride ourselves on having a flat structure focused on collaboration, teamwork, and communication with no major tiers or hierarchy. We are a small but robust team, independent enough to effortlessly pivot when required.
20/574 Plummer Street,
Port Melbourne,
Victoria, Australia 3207
We appreciate you reaching out to us. We’ll get back to you shortly, through your provided contact details.